The Mall of San Juan
At the time of construction, The Mall of San Juan was Puerto Rico’s largest construction project at 650,000sf and a cost of $475,000,000. Specialty Spray Systems was contracted to install all of the medium density fireproofing to the structure. 45,000 bags of Monokote Z106 were used and took a total of 10 months to complete. DCK Worldwide served as the general contractor.
Project Gallery
Project Details
Client: D.C.K. / Bird (joint venture)
Location: San Juan, Puerto Rico
Scope: Spray applied Monokote Z106 medium density fireproofing
Duration: 1 year
Budget: $3,000,000